1) Initiate planning effort / public scoping
2013: Publish Notice of Intent in the Federal Register
2013-2014: Public scoping period
May 2014: Publish scoping report
April 2015: Publish ACEC Evaluation Report
2) Inventory and data collection
2013-2015: Gather and analyze new data for Draft RMP/EIS
2013-2015: Geographic Information Systems data collection and cleanup for Draft RMP/EIS
3) Analysis of the Management Situation
2013-2016: Describe existing situation, current management, and opportunities for change
4) Formulate alternatives
2014-2015: Formulate a range of alternatives to analyze in the Draft RMP/EIS
Early 2015: Public comment on draft alternatives via "Preliminary Alternatives Outreach" meetings
2016-2018: Internal and cooperator review of Draft RMP/EIS
5) Draft Resource Management Plan / Environmental Impact Statement
March 2019: Draft RMP/EIS and Preliminary ANILCA Section 810 Subsistence Evaluation
5) Proposed Resource Management Plan / Final Environmental Impact Statement
2020: Publish Notice of Availability for Proposed RMP/Final EIS and Final ANILCA Section 810 Subsistence Evaluation
2020: Publish Comment Summary Report including responses to public comment received on the Draft RMP/EIS
2020: Governor consistency review and 30-day protest period
6) Records of Decision and Approved RMP
2021: Issue Record of Decision