Schedule for Development of the Browns Canyon Resource Management Plan

Future dates are estimated. Please check back for new updates. Blue highlighted row is current stage in RMP/EIS development.
 
Public views and human ecology mapping report
October 2016 - May 2017
USFS monument assessment report and BLM monument analysis of management situation addendum
October 2017 - March 2018
Develop Planning Criteria Report
July 2018 - March 2019
Public review of Planning Criteria Report 
July 2018 - March 2019
Notice of intent published
May 14, 2019
Public scoping period and meetings
May - June 2019
Develop Draft RMP/EIS – internal reviews
June 8 - October 2019
Public comment period for the Draft RMP/EIS (90 Days)
October 4, 2019 - January 2, 2020
Develop Proposed RMP/Final EIS – consider public comments; conduct internal reviews
January - April 2020
Public review and protest period for Proposed RMP/Final EIS  (30 days)
April 17 - May 18, 2020
Protest resolution (30 days)
May - June 2020
Develop and Release Approved RMP and Record of Decision
May 19 - July 24, 2020


 