Timeline
| Milestone | Target Date |
| Notice of Intent | December 5, 2019 |
| 30-day Public Scoping Period | December 5, 2019 - January 6, 2020 |
| Draft EIS Notice of Availability | June 12, 2020 |
| 90-day Public Comment Period | June 12 - September 10, 2020 |
| Final EIS Notice of Availability | November 13, 2020 |
30-day Protest Period (concurrent Governor's Consistency Review could be up to 60 days) | November 13 - December 14, 2020 |
| FWS and BLM Records of Decision | January 13, 2021 |