Project Name: Lewistown Field Office Resource Management Plan and EIS

NEPA Number: DOI-BLM-MT-L060-2014-0016-RMP-EIS

Timeline

Shedule
 
February 2014 Completed  Notice of Intent (NOI) published in the Federal Register.
2016- 2018 Completed Alternatives Development and Preparation of the Draft RMP/EIS
May 2017 Completed Notice of Availability (NOA) published in the Federal Register for the Draft RMP/EIS
Fall 2019 Completed Review and Incorporate public comments into and administrative Proposed RMP/Final EIS
February 2020 Completed Notice of Availability published in the Federal Register for Proposed RMP/Final EIS
Summer 2020     Completed Approved RMP and Record of Decision