Public views and human ecology mapping report
|
October 2016 - May 2017 |
|
USFS monument assessment report and BLM monument analysis of management situation addendum
|
October 2017 - March 2018 |
|
Develop Planning Criteria Report
|
July 2018 - March 2019 |
|
Public review of Planning Criteria Report
|
July 2018 - March 2019 |
|
Notice of intent published
|
May 14, 2019 |
|
Public scoping period and meetings
|
May - June 2019 |
|
Develop Draft RMP/EIS – internal reviews
|
June 8 - October 2019 |
|
Public comment period for the Draft RMP/EIS (90 Days)
|
October 4, 2019 - January 2, 2020 |
|
Develop Proposed RMP/Final EIS – consider public comments; conduct internal reviews
|
January - April 2020 |
|
Public review and protest period for Proposed RMP/Final EIS (30 days)
|
April 17 - May 18, 2020 |
|
Protest resolution (30 days)
|
May - June 2020 |
|
Develop and Release Approved RMP and Record of Decision
|