NEPA Number: DOI-BLM-UT-C000-2020-0001-RMP-EIS
Project Name: Highway Right-of-Way, Issuance of an Incidental Take Permit, and Resource Management Plan Amendments, Washington County, Utah

Timeline


Milestone
Target Date
Notice of Intent
December 5, 2019
30-day Public Scoping Period
December 5, 2019 - January 6, 2020
Draft EIS Notice of Availability
June 12, 2020
90-day Public Comment Period
June 12 - September 10, 2020
Final EIS Notice of Availability
November 13, 2020

30-day Protest Period (concurrent Governor's Consistency Review

could be up to 60 days)

November 13 - December 14, 2020
FWS and BLM Records of Decision
January 13, 2021