NEPA Number: DOI-BLM-UT-C030-2023-0038-EIS
Project Name: Supplemental Environmental Impact Statement to Reconsider a Highway Right-of-Way and Associated Amendment of an Incidental Take Permit, Washington County, Utah

Timeline

The public scoping period opens November 16, 2023, and closes December 21, 2023.


The draft SEIS is anticipated to be available for public review in spring 2024 and the final SEIS is anticipated to be available in September 2024. 

The settlement agreement calls for publication of a new Record of Decision (ROD) by November 2024. 

Milestone

Target Date

Notice of Intent

November 16, 2023

30-day Public Scoping Period (Now Extended)

November 16, 2023December 28, 2023

Public Scoping Open HouseDecember 6, 2023, 4:307:30 at the Dixie Center

Draft SEIS Notice of Availability

May 10, 2024

45-day Public Comment Period (extended)

May 10 - July 9, 2024

Final SEIS Notice of Availability

November 8, 2024

FWS and BLM Records of Decision

 December 2024