Identify Planning Issues and Criteria/Analysis of the Management Situation: Fall 2008
Notice of Intent: November 14, 2008
Public Scoping: Nov. 2008 - Jan. 2009
Alternatives Formulation: Spring 2009 - Spring 2010
Preparation of Draft RMP/Draft EIS: Spring 2010 - June 2013
Notice of Availability of Draft RMP and EIS: June 28, 2013
90-Day Public Comment Period: June 28, 2013 - Sept. 26, 2013
Preparation of Proposed RMP /Final EIS: Oct. 2013- May 2015
Notice of Availablity of Proposed RMP/Final EIS: May 29, 2015
Protest Period (30 days) and Governor's Consistency Review ( 60 days): June - July 2015
Record of Decision: September 21, 2015