NEPA Number: DOI-BLM-NV-0000-2022-0004-EIS
Project Name: Greenlink West Transmission Project

Project Information 

  • NEPA Number
    DOI-BLM-NV-0000-2022-0004-EIS
  • Project Name
    Greenlink West Transmission Project
  • Project Type
    EIS
  • NEPA Status
    Completed - Completed
  • Lead Office
    State Office - NV
  • Last Updated
    1/30/2026 7:21:15 AM


Project Description

What's New

For the latest information on project construction, please go to NV Energy's website at: CLICK HERE

For media inquiries on project construction, please contact NV Energy at: CLICK HERE

Draft EIS Publication

  • Initial Scheduled Date
  • Revised Target Date
  • Actual Date
    5/26/2023


Final EIS Publication

  • Initial Scheduled Date
  • Revised Target Date
  • Actual Date
    6/14/2024


Project Location

City State/Territory Zip Code County(ies)
Silverpeak Nevada 89047 Esmeralda County

Application Information

Project Dates

  • Start Date
    5/2/2022
  • End Date
    9/8/2024
  • FONSI Date


Notice of Intent Publication

  • Initial Scheduled Date
    5/2/2022
  • Revised Target Date
    5/2/2022
  • Actual Date
    5/2/2022


Record of Decision Publication

  • Initial Scheduled Date
  • Revised Target Date
  • Actual Date
    9/8/2024


Project Office Information

  • Lead Office
    State Office - NV
  • Offices
    Battle Mountain DO,   Carson City DO,   Southern Nevada DO,   State Office - NV
  • Cooperating Agencies


Contacts

  • Contact 2 Name
    Greg Helseth
  • Contact 2 Email
  • Contact 2 Phone
    (775)861-6477