NEPA Number: DOI-BLM-AZ-C010-2021-0029-EA
Project Name: Phase 3 Sandy Valley Exploration Project

Project Information 

  • NEPA Number
    DOI-BLM-AZ-C010-2021-0029-EA
  • Project Name
    Phase 3 Sandy Valley Exploration Project
  • Project Type
    EA
  • NEPA Status
    Completed - Completed
  • Lead Office
    Kingman Field Office
  • Last Updated


Project Description

What's New

The Bureau of Land Management, Kingman Field Office has issued a decision record and finding of no significant impacts for this exploration project.

Comments were accepted on the Big Sandy Inc., Sandy Valley Exploration Project (Phase 3) Environmental Assessment (EA), DOI-BLM-AZ-C010-2021-0029-EA, originally for a 30-day period beginning April 12, 2021. Based on requests received during this period the Bureau of Land Management (BLM), Colorado River District, Kingman Field Office extended the original comment period twice for a total of approximately 90-days and accepted comments from April 12, 2021, through July 10, 2021; although comments received in a timely manner after this date were also considered.

BLM received 815 individual comments during the public comment period. All the comments received were compiled and responses to substantive comments were addressed in Appendix E of the Final EA (see "Documents" on left navigation pane). Section 1.6 of the Final EA includes an overview of the public involvement efforts and modifications made to the Proposed Action based on input received. Additional coordination and consultation with the Hualapai Tribe occurred after the comment period resulting in changes to the Proposed Action and the acceptance of the Tribe as a Cooperating Agency in preparation of the Final EA. Additional information was added to the EA based on the input received from the Tribe.

Thank you for your continued interest in this project and in public lands managed by the Kingman Field Office.


Project Location

City State/Territory Zip Code County(ies)
Lake Havasu City Arizona 86406 Mohave County

Application Information

  • Applicant
    Big Sandy Inc.
  • Case File Number
    AZA-37913
  • Program
    Mining


Project Dates

  • Start Date
    3/12/2021
  • FONSI Date
    6/5/2024


Project Office Information

  • Lead Office
    Kingman Field Office
  • Offices
    Kingman FO


Contacts

  • Contact 1 Name
    Angelica Rose
  • Contact 1 Email
  • Contact 1 Phone
    (928) 505-1200


  • Contact 2 Name
    Paul Misiaszek
  • Contact 2 Email
  • Contact 2 Phone
    (928) 718-3700