NEPA Number: DOI-BLM-AK-F030-2018-0038-EIS
Project Name: Alaska Stand Alone Pipeline

Project Information 

  • NEPA Number
    DOI-BLM-AK-F030-2018-0038-EIS
  • Project Name
    Alaska Stand Alone Pipeline
  • Project Type
    EIS
  • NEPA Status
    Completed - Completed
  • Lead Office
    Central Yukon Field Office
  • Last Updated
    2/19/2026 5:00:00 PM


Project Description

What's New

The Alaska Stand Alone Pipeline (ASAP) is a proposed 733-mile pipeline that will deliver natural gas from Alaska’s North Slope to the state’s population centers in the Interior of Alaska and Southcentral Alaska.  It is being developed by the Alaska Gasline Development Corporation (AGDC), an independent corporation established by the State of Alaska.  The AGDC is chartered to ensure that Alaska’s North Slope natural gas resources are available to provide the maximum benefit and use by Alaskans. 

To review the analysis and record of decision, please visit the Documents page.

Draft EIS Publication

  • Actual Date
    6/22/2018


Final EIS Publication

  • Actual Date
    8/29/2018


Project Location

City State/Territory Zip Code County(ies)
Bettles Field Alaska 99726 Yukon-Koyukuk

Application Information

  • Applicant
    Alaska Gasline Development Corporation
  • Case File Number
    AK FF95641
  • Program
    Lands and Realty
  • Sub-Program
    Rights-of-Way


Project Dates

  • Start Date
    8/1/2014
  • End Date
    3/3/2019


Notice of Intent Publication

  • NOI Publication Date
    8/1/2014


Record of Decision Publication

  • Actual Date
    3/3/2019


Project Office Information

  • Lead Office
    Central Yukon Field Office
  • Offices
    Anchorage FO,   Central Yukon FO,   Eastern Interior FO,   Glennallen FO,   State Office - AK


Contacts

  • Contact 1 Name
    Melissa Head
  • Contact 1 Email
  • Contact 1 Phone
    (907) 474-2247