NEPA Number: DOI-BLM-AK-A020-2024-0007-EA
Project Name: Thompson Pass and Valdez Heli-skiing

Documents


December 22, 2025: The December 11 Decision Record was removed and replaced with the one signed Dec 22.
The December 11 version of the Decision Record contained a grammatical error that has been corrected in this version with strikethrough text and bold underlined and highlighted text replacing two instances of the word “or” with “and” on page 2 of the Decision Record.

December, 11, 2025: Final EA, Finding of No Significant Impact (FONSI), and Decision Record posted

August 27 - September 25, 2025 Preliminary EA Public Comment Period
The 30-day public comment period for the Preliminary EA is available until September 25, 2025. Please review the EA and the "How to submit a substantive comment" documents below. When you are ready to comment, you may click on the green button and submit your comment. Thank you for engaging on this project!

April 12, 2024: 30-day Public Scoping Comment Period Ended
The scoping period provided the public the opportunity to submit ideas, comments, and concerns for the BLM to consider when developing the Environmental Assessment (EA). The materials provided at an in-person public meeting were also made available online, below under "Public Scoping March 14 - April 12" as well as on the separate "maps" page. A summary of the scoping effort will be available in the future EA released for public review and comment. The Public Comment Summary report is available for review.

PROJECT MILESTONES:
  • October 4, 2024 - December 31, 2024: Special Recreation Permit Application Window
  • WINTER 2025 - EA DEVELOPMENT
  • SPRING/SUMMER 2025 - EA PUBLIC COMMENT PERIOD
  • FALL 2025 - SIGN EA DECISION
  • WINTER 2026 - Authorize operators for 2026- 2035 ten-year permit period