Timelines for Two Rivers EA
Acquired time limit waiver for two years
(January 2026)
10/31/2024 Finish drafting of Tribal
MOA
10/15/2024 WYSO comments submitted EA
10/22/2024 WYSO sends EA to BLM SOL
10/22/2024 FWS sends EA to FWS SOL
10/22/2024 CoOp Agencies for review
11/5//2024 FWS SOL review completed
11/29/2024-Fully signed and executed MOA & signed DR
12/2024- Issue ROW