| SEORMP TASKS AND MILESTONES | Estimated Timeline |
|---|---|
| Notice of Intent published in Federal Register | April 8, 2010 |
| Develop and Publish the Draft RMP Amendment/EIS | 2017 – 2019 |
|
Publish Draft RMP/Draft EIS in Federal Register, post to ePlanning
|
May 31, 2019 |
|
90-day Public Comment Period
|
May 31, - August 28, 2019 |
|
Public Meetings
|
June 24, 25, 26, 2019 |
| Develop the Proposed RMP/Final EIS | 2019-2023 |
|
Publish Final RMP/Final EIS in Federal Register; post to ePlanning
|
June 16th, 2023 |
|
60-day Governor’s Consistency Review
|
Sixty days following publication of the PRMPA/FEIS in the Federal Register |
|
30-day Protest Period for Plan Amendment
|
Thirty days following publication of the PRMPA/FEIS in the Federal Register Protests must be received by close of business on Monday, July 17th, 2023 |
| Develop the Record of Decision/Approved RMP | Summer 2023 |
| Publish Approved RMP Amendment/Record of Decision in the Federal Register; post to ePlanning | February 26, 2024 |