SEORMP TASKS AND MILESTONES Estimated Timeline 
Notice of Intent published in Federal Register April 8, 2010
Develop and Publish the Draft RMP Amendment/EIS

2017 – 2019

Publish Draft RMP/Draft EIS in Federal Register, post to ePlanning
May 31, 2019
90-day Public Comment Period
May 31, - August 28, 2019
Public Meetings
June 24, 25, 26, 2019
Develop the Proposed RMP/Final EIS 2019-2023
Publish Final RMP/Final EIS in Federal Register; post to ePlanning
June 16th, 2023
60-day Governor’s Consistency Review

Sixty days following publication

of the PRMPA/FEIS in the Federal Register 

30-day Protest Period for Plan Amendment

Thirty days following publication of the PRMPA/FEIS in the Federal Register

Protests must be received by close of business on Monday, July 17th, 2023

Develop the Record of Decision/Approved RMP Summer 2023
Publish Approved RMP Amendment/Record of Decision in the Federal Register; post to ePlanning February 26, 2024

      