Project Name: Silver Rock Transmission Line

NEPA Number: DOI-BLM-UT-0000-2026-0006-EIS

Project Information 

  • NEPA Number
    DOI-BLM-UT-0000-2026-0006-EIS
  • Project Name
    Silver Rock Transmission Line
  • Project Type
    EIS
  • NEPA Status
    Planned - Preparation and Planning
  • Lead Office
    State Office - UT
  • Last Updated
    09/02/2026 - 10:53 AM


Project Description

What's New

 


September 02, 2026 - The publication of the Notice of Intent releases on September 3, 2026, and will initiate the 30-day scoping period which is scheduled to conclude on October 5, 2026. The BLM will host two virtual public meetings at the dates and times below, please use the link to register for the meeting you would like to attend.

You may submit comments related to the Project by October 5, 2026, by any of the following methods:

·         BLM National NEPA Register: https://eplanning.blm.gov/Project-Home/?id=4e1e1343-925b-f111-bec6-001dd8029ed0

o   Click “Participate Now” to the right of the document link, enter your comment information, and click “Submit.”

·         Delivered comments to:

Bureau of Land Management

ATTN: Michelle Campeau 

176 East D.L. Sargent Drive

Cedar City, UT 84721

 

Before including addresses, phone numbers, email addresses, or other personal identifying information in your comment, be aware that entire comments – including personal identifying information – may be made publicly available at any time. While commenters can request that personal identifying information be withheld from public review, the BLM cannot guarantee that we will be able to do so.

 

List of Events

Draft EIS Publication

  • Initial Scheduled Date
    6/25/2027


Final EIS Publication

  • Initial Scheduled Date
    4/28/2028


Project Location

City State/Territory Zip Code County(ies)
Milford Utah 84751 Beaver

Application Information

  • Applicant
    Silver Rock Transmission, LLC
  • Case File Number
    UTUT106738853
  • Program
    Lands and Realty
  • Sub-Program
    Rights-of-Way


Project Dates

  • Start Date
    9/3/2026


Notice of Intent Publication

  • NOI Publication Date
    9/3/2026


Record of Decision Publication

  • Initial Scheduled Date
    7/28/2028


Project Office Information

  • Lead Office
    State Office - UT
  • Offices
    Caliente FO,   Cedar City FO,   Fillmore FO,   Las Vegas FO,   State Office - UT


Contacts

  • Contact 1 Name
    Silver Rock Project Email
  • Contact 1 Email
  • Contact 1 Phone
    435-865-3000


  • Contact 2 Name
    Media Contact
  • Contact 2 Email
  • Contact 2 Phone
    801-539-4001