L.5. 5.0 ENGINEERING BEST MANAGEMENT PRACTICES

Road maintenance, construction, and any other related travel and transportation management will be mandated by BLM Manual 9113. BLM Manual 9113 provides for BMPs to be used in evaluating, maintaining, and constructing BLM travel and transportation routes. As stated in Manual 9113, “Bureau roads must be designed to an appropriate standard no higher than necessary to accommodate their intended functions adequately (timber hauling administrative access, public travel); and design, construction, and maintenance activities must be consistent with national policies for safety, aesthetics, protection and preservation of cultural, historic, and scenic values, and accessibility for the physically handicapped. The following is a list of BMPs that are recommended but not binding for road maintenance practices:

  1. Design roads to minimize total disturbance, to conform with topography, and to minimize disruption of natural drainage patterns.

  2. Base road design criteria and standards on road management objectives such as traffic requirements of the proposed activity and the overall TP, economic analysis, safety requirements, resource objectives, and minimizing damage to the environment.

  3. Locate roads on stable terrain such as ridge tops, natural benches, and flatter transitional slopes near ridges, and valley bottoms, and moderate side slopes and away from slumps, slide prone areas, concave slopes, clay beds, and where rock layers dip parallel to the slope. Locate roads on well-drained soil types; avoid wet areas when possible.

  4. Construct cut and fill slopes to be approximately 3 horizontal (h):1 vertical (v) or flatter where feasible. Locate roads to minimize heights of cutbanks. Avoid high, steeply sloping cutbanks in highly fractured bedrock.

  5. Avoid headwalls, midslope locations on steep, unstable slopes, fragile soils, seeps, old landslides, side slopes in excess of 70 percent, and areas where the geologic bedding planes or weathering surfaces are inclined with the slope. Implement extra mitigation measures when these areas cannot be avoided.

  6. Construct roads for surface drainage by using outslopes, crowns, grade changes, drain dips, waterbars and in-sloping to ditches as appropriate.

  7. Sloping the road base to the outside edge for surface drainage is normally recommended for local spurs or minor collector roads where low-volume traffic and lower traffic speeds are anticipated. This is also recommended in situations where long intervals between maintenance will occur and where minimum excavation is wanted. Out-sloping is not recommended on steep slopes. Sloping the road base to the inside edge is an acceptable practice on roads with steep side slopes and where the underlying soil formation is very rocky and not subject to appreciable erosion or failure.

  8. Crown and ditching is recommended for arterial and collector roads where traffic volume, speed, intensity and user comfort are considerations. Recommended gradients range from 0 to 15 percent where crown and ditching may be applied, as long as adequate drainage away from the road surface and ditch lines is maintained.

  9. Minimize excavation, when constructing roads, through the use of balanced earthwork, narrowing road widths, and end hauling where side slopes are between 50 and 70 percent.

  10. If possible, construct roads when soils are dry and not frozen. When soils or road surfaces become saturated to a depth of 3 inches, BLM-authorized activities should be limited or ceased unless otherwise approved by the authorized officer.

  11. Consider improving inadequately surfaced roads that are to be left open to public traffic during wet weather with gravel or pavement to minimize sediment production and maximize safety.

  12. Retain vegetation on cut slopes unless it poses a safety hazard or restricts maintenance activities. Roadside brushing of vegetation should be done in a way that prevents disturbance to root systems and visual intrusions (i.e., avoid using excavators for brushing).

  13. Retain adequate vegetation between roads and streams to filter runoff caused by roads.

  14. Avoid riparian/wetland areas where feasible; locate in riparian/wetland areas only if the roads do not interfere with the attainment of resource objectives.

  15. Minimize the number of unimproved stream crossings. When a culvert or bridge is not feasible, locate drive-through (low water crossings) on stable rock portions of the drainage channel. Harden crossings with the addition of rock and gravel if necessary. Use angular rock if available.

  16. Locate roads and limit activities of mechanized equipment within stream channels to minimize their influence on riparian areas. When crossing a stream is necessary, design the approach and crossing perpendicular to the channel, where practicable. Locate the crossing where the channel is well defined, unobstructed, and straight.

  17. Avoid placing fill material in floodplain unless the material is large enough to remain in place during flood events.

  18. Use drainage dips instead of culverts on level 2 roads where gradients will not present a safety issue. Locate drainage dips in such a way so that water will not accumulate or where outside berms prevent drainage from the roadway. Locate and design drainage dips immediately upgrade of stream crossings and provide buffer areas and catchment basins to prevent sediment from entering the stream.

  19. Construct catchment basins, brush windrows, and culverts in a way to minimize sediment transport from road surfaces to stream channels. Install culverts in natural drainage channels in a way to conform with the natural streambed gradients with outlets that discharge onto rocky or hardened protected areas.

  20. Design and locate water crossing structures in natural drainage channels to accommodate adequate fish passage, provide for minimum impacts to water quality, and to be capable of handling a 100-year event for runoff and floodwaters.

  21. Use culverts that pass, at a minimum, a 25-year storm event or have a minimum diameter of 24 inches for permanent stream crossings and a minimum diameter of 18 inches for road cross drains.

  22. Replace undersized culverts and repair or replace damaged culverts and downspouts. Provide energy dissipaters at culvert outlets or drainage dips.

  23. Locate culverts or drainage dips in such a manner as to avoid discharge onto unstable terrain such as headwalls or slumps. Provide adequate spacing to avoid accumulation of water in ditches or road surfaces. Culverts should be placed on solid ground to avoid road failures.

  24. Proper sized aggregate and riprap should be used during culvert construction. Place riprap at culvert entrance to streamline waterflow and reduce erosion.

  25. Establish adapted vegetation on all cuts and fill immediately following road construction and maintenance.

  26. Remove berms from the downslope side of roads, consistent with safety considerations.

  27. Leave abandoned roads in a condition that provides adequate drainage without further maintenance. Close abandoned roads to traffic. Physically obstruct the road with gates, large berms, trenches, logs, stumps, or rock boulders as necessary to accomplish permanent closure.

  28. Abandon and rehabilitate roads that are no longer needed. Leave these roads in a condition that provides adequate drainage. Remove culverts.

  29. When plowing snow for winter use of roads, provide breaks in snow berms to allow for road drainage. Avoid plowing snow into streams. Plow snow only on existing roads.

  30. Maintenance should be performed to conserve existing surface material, retain the original crowned or out-sloped self-draining cross section, prevent or remove rutting berms (except those designed for slope protection) and other irregularities that retard normal surface runoff. Avoid wasting loose ditch or surface material over the shoulder where it can cause stream sedimentation or weaken slump-prone areas. Avoid undercutting back slopes.

  31. Do not disturb the toe of cut slopes while pulling ditches or grading roads. Avoid sidecasting road material into streams.

  32. Grade roads only as necessary. Maintain drain dips, waterbars, road crown, in-sloping and outsloping, as appropriate, during road maintenance.

  33. Maintain roads in special areas according to special area guidance. Generally, retain roads within existing disturbed areas and sidecast material away from the special area.

  34. When landslides occur, save all soil and material usable for reclamation or stockpile for future reclamation needs. Avoid sidecasting of slide material where it can damage, overload, and saturate embankments, or flow into down-slope drainage courses. Reestablish vegetation as needed in areas where vegetation has been destroyed due to sidecasting.

  35. Strip and stockpile topsoil ahead of construction of new roads, if feasible. Reapply soil to cut and fill slopes prior to revegetation.