U.S. DEPARTMENT OF THE INTERIOR  BUREAU OF LAND MANAGEMENT  
ePlanning DOI-BLM-NM-L000-2016-0142-EIS (Southline Transmission Line Project)  
> NEPA Register > DOI-BLM-NM-L000-2016-0142-EIS
NEPA Project Summary 
NEPA #:  DOI-BLM-NM-L000-2016-0142-EIS Status:  Completed
Project Name:  Southline Transmission Line Project Decision Date:  04/21/2016
EIS OEPC #:  FONSI Date: 
Applicant:  Southline Transmission, LLC    
Case File Number/:
Project Number 
NMNM 124104, AZA 035681    
Start Date:  12/22/2010    
End Date:  04/21/2016    
 
Project Description:
The Southline Transmission Line Project consists of two sections: the New Build and the Upgrade sections. The New Build Section is approximately 240 miles of new double-circuit 345-kilovolt (kV) transmission line along with substation expansions, access roads and associated infrastructure. The Upgrade Section is approximately 120 miles of Western Area Power Administration’s (Western’s) existing 115-kV transmission line that is being upgraded to a double-circuit 230-kV transmission line as well as substation expansions, access roads, and associated infrastructure. In the New Build Section, Southline will construct and operate approximately 240 miles of new double-circuit 345-kilovolt (kV) transmission line in a new 200-foot-wide ROW between the Afton Substation, south of Las Cruces, New Mexico, and the Apache Substation, south of Willcox, Arizona. In the New Build Section, one new substation, the Midpoint Substation, will be constructed in Luna County, New Mexico; two existing substations in New Mexico and one in Arizona will be expanded. In the Upgrade Section, Southline will upgrade approximately 120 miles of Western’s existing Saguaro–Tucson and Tucson–Apache 115-kV transmission lines in a 100-foot-wide existing ROW to a double-circuit 230-kV transmission line from the Apache Substation to the Saguaro Substation northwest of Tucson, Arizona. In some places along the existing ROW, up to an additional 50-foot ROW will be needed. Approximately 2 miles of new-build double-circuit 230-kV electric transmission line would be needed to interconnect with the existing Tucson Electric Power Company Vail Substation, located southeast of Tucson and just north of the existing 115-kV Tucson-Apache line. Twelve substations in Arizona will be expanded to accommodate new equipment associated with the upgrade; in some cases, expansion may require a separate yard. A notice of intent (NOI) to prepare the EIS for the Project was published in the Federal Register on April 4, 2012. The notice of availability (NOA) for the Draft EIS was published on April 11, 2014 in the Federal Register. The NOA for the Final EIS was published on November 10, 2015 in the Federal Register. The Record of Decision (ROD) was signed by the BLM Las Cruces District Manager on April 21, 2016.
Project Location:
The project begins at the Afton Substation southwest of Las Cruces, New Mexico, and traverses approximately 360 miles west where it terminates at the Saguaro Substation northwest of Tucson, Arizona.
 
Project Lead:  Mark Mackiewicz    
Phone Number:  (435) 636-3616    
Email Address:  mmackiew@blm.gov    
Office(s):  Tucson FO
Safford FO
Las Cruces DO
Lead Office:  Las Cruces DO
Counties:  Pima
Dona Ana
Grant
Hidalgo
Luna
Cochise
   
 
Program(s):  Lands and Realty Subprogram(s):  Rights-of-Way
Cooperating Agencies:     
 

Documents: 
Document Name Release Date Available Formats Public Comment Period
Record of Decision_Southline Transmission Line Project 04/21/2016 SLT ROD 042216_508.pdf (24740 KB) 
Final EIS_Volumes 1-4_Southline Transmission Line Project 04/21/2016  (4 Files)
Final_EIS_Appendices 04/21/2016  (14 Files)
 

Maps: 
PDF Maps 
  Map Name Release Date Number of Maps
Overview Map of Southline Transmission Line Project 04/21/2016 1

Last Updated:  07/12/2017 15:50:26 MDT