U.S. DEPARTMENT OF THE INTERIOR  BUREAU OF LAND MANAGEMENT  
ePlanning DOI-BLM-WY-D030-2017-0132-DNA (Chokecherry and Sierra Madre Wind Energy Project Phase II Haul Road and Facilities)  
> NEPA Register > DOI-BLM-WY-D030-2017-0132-DNA
NEPA Project Summary 
NEPA #:  DOI-BLM-WY-D030-2017-0132-DNA Status:  Completed
Project Name:  Chokecherry and Sierra Madre Wind Energy Project Phase II Haul Road and Facilities Decision Date:  03/09/2018
EIS OEPC #:  FONSI Date: 
Applicant:  Power Company of Wyoming LLC    
Case File Number/:
Project Number 
ROW WYW-167155    
Start Date:  06/29/2017    
End Date:  04/10/2018    
 
Project Description:
The CCSM Project Phase II Haul Road and Facilities, includes the second portion of the CCSM Project on the east side of the project area. The CCSM project was analyzed under a programmatic Environmental Impact Statement and the Record of Decision was signed by the Secretary of the Interior on October 9, 2012. In the ROD, BLM determined that over 200,000 acres within the CCSM Project Area are suitable for wind energy development subject to the requirements described under the Selected Alternative in the ROD. Phase II portions of the CCSM Project Haul Road, water facilities, and laydown yards would be constructed. The Phase II Haul Road includes 59.3 miles of new roads. It also includes the establishment of three laydown yards Severson Flats, Junction and Sage Creek that are proposed be 4 to 5 acres in size each. Water would be piped to the water stations. Piping would be done utilizing High Density Polyethylene (HDPE) or Polyvinyl chloride (PVC) plastic pipes between 2 inch and 8 inch in diameter. These pipelines may be above-ground or buried depending upon the location and timing of construction.
Project Location:
South of Rawlins Wyoning
 
Project Lead:  Heather Schultz    
Phone Number:  (307) 328-4215    
Email Address:  hschultz@blm.gov    
Office(s):  Rawlins FO Lead Office:  Rawlins FO
Counties:  Carbon    
 
Program(s):  Renewable Energy Subprogram(s):  Wind Energy
Cooperating Agencies:     
 

Documents: 
Document Name Release Date Available Formats Public Participation
CCSM_SPOD5_Phase_II_Haul_Roads_and_Infrastructure 03/09/2018 DOI-BLM-WY-D030-2017-0132-DNA_CCSM_SPOD5_Phase_II_Haul_Roads_and_Infrastructure.pdf (355 KB) 
CCSM_SPOD5_DNA_Memo 03/09/2018 2017_11_30_CCSM_SPOD5_DNA_Memo.pdf (2966 KB) 
 

Last Updated:  04/10/2018 12:59:43 MDT