U.S. DEPARTMENT OF THE INTERIOR  BUREAU OF LAND MANAGEMENT  
ePlanning DOI-BLM-UT-Y010-2018-0181-EA (Green River City Proposed Natural Gas Pipeline)  
> NEPA Register > DOI-BLM-UT-Y010-2018-0181-EA
NEPA Project Summary 
NEPA #:  DOI-BLM-UT-Y010-2018-0181-EA Status:  Decision and Appeal
Project Name:  Green River City Proposed Natural Gas Pipeline Decision Date: 
EIS OEPC #:  FONSI Date: 
Applicant:  Green River City    
Case File Number/:
Project Number 
UTU-92253    
Start Date:  07/02/2018    
End Date:     
 
Project Description:
The proposed project is to construct and operate approximately 16 miles of natural gas pipeline in Grand County, Utah. The proposed pipeline would transport dry natural gas from the existing Greentown Gas Processing Facility to Green River City’s proposed Gate Station. The proposed pipeline would be composed of 6-inch diameter buried steel pipeline and associated infrastructure, such as valves, meters, and pigging constructed within a 50-foot wide temporary construction right-of-way corridor and operated and maintained within a 30-foot corridor. The pipeline would be buried approximately three feet below existing grade. Additionally, six staging areas are proposed for construction use.
Project Location:
Project components would be located on private,. Municipal, state and BLM administered lands in: T 21 S, R 16 E, secs. 13, 14 T 21 S, R 17 E, secs. 18, 20 21, 27, 28, 34, 35 T 22 S, R 17 E, sec. 1 T 22 S, R 18 E, secs. 4, 5, 6, 9, 16, 20, 29 The proposed project would closely follow the previously approved Gray Canyon Energy pipeline route.
 
Project Lead:  Lisa Wilkolak    
Phone Number:  (435) 259-2140    
Email Address:  lwilkolak@blm.gov    
Office(s):  Moab FO Lead Office:  Moab FO
Counties:  Grand    
 
Program(s):  Lands and Realty Subprogram(s):  Rights-of-Way
Cooperating Agencies:     
 

Documents: 
Document Name Release Date Available Formats Public Participation
EA 08/23/2019 18-0181.pdf (6615 KB)   
 

Last Updated:  08/23/2019 10:17:05 MDT