Decision Record Issued
The Bureau of Land Management (BLM), Carson City District, Stillwater Field Office has issued a Decision for the Tungsten Mountain Geothermal Development Project EA # DOI-BLM-NV-C010-2016-0016-EA, proposed by Ormat.

Ormat is proposing to construct, operate and maintain the Tungsten Mountain Geothermal Development Project. This project is located on public lands in Churchill County, Nevada.  The geothermal portions of the Project are located within the Tungsten Mountain Geothermal Unit (NVN-88836X), which is comprised of federal geothermal leases N-85715, N- 86897, N-86898, N 88428, N-90744 and N-92480. This EA analyzes the potential impacts from the proposed development of this project including: the construction and operation of two geothermal power plants, up to 24 geothermal production and injection well pads and wells, geothermal fluid pipelines, access roads, approximately 17 miles of a generation tie (gen-tie) line, and ancillary facilities.

 
The EA was available for review for a 30-day public comment period through January 21, 2016. 
The Decision Record and Finding of No Significant Impact was signed on March 25, 2016.

 
 
 
 
The Dear Reader Letter, Final EA and Appendices, Decision Record and Finding of No Significant Impacts are available by clicking on the "Documents" link on the left hand side of the page.  The maps figures are available by clicking on the "Maps" or "Documents" links on the left hand side of the page.  Refer to the information provided under the "Contact Information" link on the left for how to submit comments on this document or for other information.