Timeline 
 
 
 
Steps in the Planning Process (future steps are highlighted in yellow):

Notice of Intent: May 2010

Scoping Period: Oct. 2010

Develop Draft RMPs/EIS: Oct. 2010-July 2015

Release Draft RMPs/EIS: July 2015

Public Comment Period: July 17, 2015-Nov. 16, 2015

Prepare Proposed RMPs/Final EIS: Fall 2015

Release Proposed RMPs/Final EIS: Sept. 02, 2016

30-day Protest Period: Oct. 03, 2016

Governor’s Consistency Review (Minimum of 60 days): Oct. 25, 2016

3 Records of Decision: Dec. 21, 2016

Plan Implementation, Monitoring, Evaluation