U.S. DEPARTMENT OF THE INTERIOR  BUREAU OF LAND MANAGEMENT  
ePlanning DOI-BLM-CO-S050-2010-0001-RMP-EIS (Uncompahgre Field Office Resource Management Plan)  
> Land Use Planning Register > DOI-BLM-CO-S050-2010-0001-RMP-EIS > Timeline
  
Find Whole Words Only
Home
Documents & Reports
Contact Information
Timeline
Issues
News
How to get Involved
    Meetings
Maps
    Data
Links
FAQs
Last Updated:
04/10/2020 08:34:56 MDT
Timeline 
Uncompahgre Proposed RMP Cover


The Record of Decision/Approved RMP was signed on April 2 and issued on April 10, 2020.
 
 
 
*FEBRUARY 25, 2010 - Notice of Intent published in Federal Register

*JANUARY 12 – FEBRUARY 3, 2010 - Public Scoping Meetings held

*FEBRUARY 25 – MARCH 29, 2010 - Public Scoping Period

*MARCH 9–17, 2010 - Economic Strategy Workshops held

*JULY 2010 - Scoping Summary Report issued

*SUMMER 2010 – FALL 2014 - Alternatives formulated and Draft Environmental Impact Statement (EIS) prepared

*JUNE 3 – NOVEMBER 1, 2016 - Draft Resource Management Plan (RMP)/Draft EIS released for public review and extended Public Comment Period

*NOVEMBER 2016 – LATE SUMMER 2017 - Public comments on the Draft RMP/Draft EIS parsed and evaluated

*FALL 2017 – SPRING 2019 - Proposed RMP/Final EIS formulated, reflecting substantive public comments and new DOI/BLM policies

*JUNE 28, 2019 - Proposed RMP/Final EIS released, initiating 30-day Public Protest Period (that closed July 29, 2019) and 60-day Governor's Consistency Review

*APRIL 10, 2020 - Record of Decision/Approved RMP signed and issued.


*Indicates a completed step