Timeline 

The following list reflects the known dates and projected timeframes for the Uncompahgre RMP planning effort.  Please check back regularly, as the schedule will be updated as dates become more firmly established.
 
 
 
 
*FEBRUARY 25, 2010 - Notice of Intent published in Federal Register

*JANUARY 12-FEBRUARY 3, 2010 - Public Scoping Meetings held


*FEBRUARY 25-MARCH 29, 2010 - Public Scoping Period

*MARCH 9-17, 2010 - Economic Strategy Workshops held

*JULY 2010 - Scoping Summary Report issued

*SUMMER 2010-FALL 2014 - Alternatives formulated and Draft Environmental Impact Statement (EIS) prepared

*JUNE 3-NOVEMBER 1, 2016 - Draft Resource Management Plan (RMP)/Draft EIS released for public review and extended comment period

NOVEMBER 2016-SPRING 2017 - Evaluate comments received on the Draft RMP/Draft EIS

SUMMER-FALL 2017 - Prepare Proposed RMP and Final EIS

WINTER 2017-2018 - Release Proposed RMP and Final EIS for 30-day public review and protest period

SPRING 2018 - Resolve protests

FALL 2018 - Issue Approved RMP and signed Record of Decision


*Indicates a completed step