Timeline 
Uncompahgre Proposed RMP Cover


The following reflects the known dates and projected timeframes for the Uncompahgre RMP planning effort.  Please check back regularly, as the schedule will be updated as dates become more firmly established.
 
 
 
*FEBRUARY 25, 2010 - Notice of Intent published in Federal Register

*JANUARY 12-FEBRUARY 3, 2010 - Public Scoping Meetings held

*FEBRUARY 25-MARCH 29, 2010 - Public Scoping Period

*MARCH 9-17, 2010 - Economic Strategy Workshops held

*JULY 2010 - Scoping Summary Report issued

*SUMMER 2010-FALL 2014 - Alternatives formulated and Draft Environmental Impact Statement (EIS) prepared

*JUNE 3-NOVEMBER 1, 2016 - Draft Resource Management Plan (RMP)/Draft EIS released for public review and extended Public Comment Period

*NOVEMBER 2016-LATE SUMMER 2017 - Public comments on the Draft RMP/Draft EIS parsed and evaluated

*FALL 2017-SPRING 2019 - Proposed RMP/Final EIS formulated, reflecting substantive public comments and new DOI/BLM policies

JUNE 28, 2019 - Proposed RMP/Final EIS released, initiating 30-day Public Protest Period (that closed July 29, 2019) and 60-day Governor's Consistency Review

LATE SUMMER 2019 - Respond to protests and issue Approved RMP and signed Record of Decision


*Indicates a completed step