Timeline 
 
 
 
The process to develop the Environmental Impact Statement (EIS) will include public involvement at a few key stages highlighted in bold below:

  Public Scoping - 60 days - January 21, 2016 - March 21, 2016 (Ended)

♦  Development of alternatives and preparation of the Draft EIS - February - October 2016 (Ended)

  Public Comment period for the Draft EIS - 90 days - (Ended)

♦  Comment management and revisions to prepare the Final EIS - November 2016 - April 2017 (Ended)

♦  Public Availability and Protest period for the Final EIS

 
 
♦  Protest period (Ended on November 19, 2017)

♦  Resolution of all protests and preparation of the Record of Decision - Winter 2018

♦  Issuance of the Record of Decision finalizing the terms of the Plan Amendment - No later than March 2018