Timeline 
The BLM is currently preparing the Draft Eastern Colorado Resource Management Plan/Environmental Impact Statement, which the agency expects to release for public comment in 2018.

The official scoping period for the Eastern Colorado RMP began June 1, 2015, and ran until July 31, 2015. Since then, many reports pertinent to plan development have been released. See Documents & Reports on the left for further information or to view/download these reports. 
 
 
 
 
Planning Process Timeline (Future Dates Are Tentative)
___________________________________________________________________________________________________________________________
Publish notice of intent in the Federal Register June 1, 2015
Public envisioning May–June 2015 
Public scoping June–July 2015
Develop preliminary alternatives and basis for analysis October 2015–February 2017
Public review of preliminary alternatives and basis for analysis March 8–May 5, 2017
Develop Draft Eastern Colorado RMP/EIS 2017-2018
Publish Draft Eastern Colorado RMP/EIS 2018
Public review and comment period for the Draft RMP/EIS For 90 days after release of the draft RMP/EIS
Develop Proposed RMP/Final EIS 2018-2019
Publish Proposed RMP/Final EIS 2019
Public review and protest period for the Proposed RMP/final EIS For 30 days after release of proposed RMP/final EIS
Develop Record of Decision and Approved RMP 2019
Publish Record of Decision and Approved RMP 2019
The public is invited to participate during plan development stages that are shaded in gray. Red text denotes the current stage.