General Lewistown RMP Schedule

The Lewistown RMP schedule is estimated as follows.  Actual dates may vary.
 

Lewistown RMP

Projected Schedule – Key Milestones

(Revised 8/31/16)

Task

Estimated

Start Date

Target Completion Date

     

Preparation Plan

 

February 2013

Notice of Intent

 

February 10,  2014

Scoping Period

February 10,  2014

April 11, 2014

Public Comment Analysis/Summary

 

April-June 2014

Final Analysis of the Management Situation

May 2013

September 2014

VRI/Travel/LWC/Trails Inventories

June 2013

June 2015

Alternatives Development

September 30, 2014

December 4, 2014

Preparation of the Preliminary DRMP/DEIS

September 2014

June 2016

WO/WO SOL Review DRMP/DEIS

June 29, 2016

September 30, 2016

NOA DRMP/DEIS (90-Day Public Comment Period)

October 2016

December 2016

News Release/Public Meetings

October 2016

December 2016

Public Comment Analysis

December 2016

February 2017

Preparation of the Proposed RMP/Final EIS

February 2017

April 2017

Finalize Proposed RMP/Final EIS

May 2017

May 2017

WO/WO SOL Review PRMP/FEIS

May 2017

July 2017

Issue Proposed RMP/Final EIS

 

June 2017

Governor’s Consistency Review (60 days)

June 2017

August 2017

30-day Public Protest Period

June 2017

July 2017

Protest Resolution

July 2017

September 2017

NOA of the ROD

 

December 2017