Timeline 
 
 
 



General Lewistown RMP Schedule

The Lewistown RMP schedule is estimated as follows.  Actual dates may vary.

Lewistown RMP

Projected Schedule – Key Milestones

(revised 7/21/15)

Task

Estimated

Start Date

Target Completion Date

     

Preparation Plan

 

February 2013

Notice of Intent

 

February 10,  2014

Scoping Period

February 10,  2014

April 11,  2014

Public Comment Analysis/Summary

 

April-June 2014

Final Analysis of the Management Situation

May 2013

September 2014

VRI/Travel/LWC/Trails Inventories

June 2013

June 2015

Alternative Development

Sept. 30, 2014

August 5, 2015

Preparation of the Preliminary DRMP/DEIS

Sept. 2014

April 2016

WO/WO SOL Review DRMP/DEIS

January 28, 2016

March 9, 2016

NOA DRMP/DEIS (90-day Public Comment Period)

April 27, 2016

July 26, 2016

News Release/Public Meetings

April 27, 2016

July 26, 2016

Public Comment Analysis

July 27, 2016

Sept. 21, 2016

Preparation of the Proposed RMP/Final EIS

Nov. 24, 2016

January 25, 2017

Finalize Proposed RMP/Final EIS

January 26, 2017

February 15, 2017

WO/WO SOL Review PRMP/FEIS

February 16, 2017

April 19, 2017

Issue Proposed RMP/Final EIS

 

March 29, 2017

Governor’s Consistency Review (60 days)

March 15, 2017

May 14, 2017

30-day Public Protest Period

March 29, 2017

April 28, 2017

Protest Resolution

May 1, 2017

June 9, 2017

NOA of the ROD

 

Sept. 15, 2017