Timeline 
The BLM released the Dominguez-Escalante National Conservation Area Proposed Resource Management Plan and Final Environmental Impact Statement for a 30-day protest period on June 30, 2016. The protest period ended on July 31, 2016.

The BLM released the Draft RMP and EIS for the D-E NCA for public review on May 17, 2013. This initiated a public comment period, which ended on September 23, 2013.

Click on Documents & Reports in the menu to the left to view or download the Proposed RMP and other documents.
 
 
 
Steps in the Development of the Dominguez-Escalante Resource Management Plan
(The current step is highlighted in yellow)
Task Completion Date
Issue Notice of Intent (NOI) August 2010
Conduct Scoping Initiated August 2010. Report released March 2011
Analyze the Management Situation Report released July 2011
Develop Alternatives Completed January 2012
Analyze Effects of Alternatives Completed March 2012
Develop a Preferred Alternative Completed June 2012
Prepare a Draft RMP Competed March 8, 3013
Public Comment Period May 17, 2013, to September 23, 2013
Prepare a Proposed RMP Released July 2016
30-Day Protest Period Ended July 31, 2016
Governor's Consistency Review (60 days minimum) Scheduled for completion in 2016
Prepare Record of Decision Scheduled for completion in 2016
Additional Comment Period (only done if significant changes were made from draft to ROD. Minimum of 30 days) To be determined
Sign Record of Decision Scheduled for completion in 2016
Plan Implementation, Monitoring, and Evaluation To be determined