NEPA Number: DOI-BLM-UT-C030-2010-0001-RMP-EIS
Project Name: Resource Management Plans (RMP) for the Beaver Dam Wash & Red Cliffs National Conservation Areas, and Plan Amendment for the St. George Field Office RMP

Timeline

Steps in the Planning Process (future steps are highlighted in yellow):

Notice of Intent: May 2010

Scoping Period: Oct. 2010

Develop Draft RMPs/EIS: Oct. 2010-July 2015

Release Draft RMPs/EIS: July 2015

Public Comment Period: July 17, 2015-Nov. 16, 2015

Prepare Proposed RMPs/Final EIS: Fall 2015

Release Proposed RMPs/Final EIS: Sept. 02, 2016

30-day Protest Period: Oct. 03, 2016

Governor’s Consistency Review (Minimum of 60 days): Oct. 25, 2016

3 Records of Decision: Dec. 21, 2016

Plan Implementation, Monitoring, Evaluation

 

Calendar