NEPA Number: DOI-BLM-CO-N030-2008-0001-RMP-EIS
Project Name: Grand Junction Field Office Resource Management Plan

Timeline

Resource Management Plan Timeline
2008 – Initiate Resource Management Plan (RMP) Revision

October 2008 – Initiated Public Scoping

August 2009 – Analysis of Management Situation
    - Develop Draft RMP

January 2013 – Public Comment Period on Draft RMP/EIS
    - Review Comments
    - Develop Proposed RMP

Septerber 2014 – Develop Proposed RMP/Final EIS

April 2015 – Proposed RMP/Final EIS Protest Period

April 2015 – Proposed RMP/Final EIS Governor’s Consistency Review

May 2015 – Resolve Protests

May - July 2015 – Develop Approved RMP/ROD

August 2015 – Issue Record of Decision for the Approved RMP and Travel Management Plan (TMP)


 