Project Name: Greenlink North 525 kV Transmission Line Project

NEPA Number: DOI-BLM-NV-0000-2022-0002-RMP-EIS

Project Information 

  • NEPA Number
    DOI-BLM-NV-0000-2022-0002-RMP-EIS
  • Project Name
    Greenlink North 525 kV Transmission Line Project
  • Project Type
    RMP Amendment - EIS
  • NEPA Status
    In Progress - Public Review and Comment Period
  • Lead Office
    State Office - NV
  • Last Updated
    7/23/2026 5:00:00 PM


Project Description

What's New

July 24, 2026

The Bureau of Land Management has opened a 30-day public comment period on the significant changes in Alternative E (Preferred Alternative) and their effects on the greater sage-grouse.

This comment period will end on August 24, 2026. Comments will not be considered after the close of the comment period.

  • There will be no new protest period.
  • There will be no public meetings.
  • The Bureau of Land Management is not required to wait 30-days after the conclusion of this comment period to issue the Record of Decision for this project.
  • The Bureau of Land Management will publish responses to substantive comments with the Record of Decision. Substantive comments would be on changes to management directions and land use allocation for major rights-of-ways in Alternative E (Preferred Alternative) and their effects on the greater sage-grouse.

Note: due to upgrades to the ePlanning system in January 2026, there is now a maximum file size of 25 mb per document.

For media inquires, contact: Rita Henderson at [email protected].

Draft EIS Publication

  • Initial Scheduled Date
    9/11/2024
  • Actual Date
    9/13/2024


Final EIS Publication

  • Initial Scheduled Date
    5/23/2025
  • Actual Date
    5/23/2025


Project Location

City State/Territory Zip Code County(ies)
Eureka Nevada 89316 Eureka

Application Information

  • Applicant
    NV Energy
  • Case File Number
    NVN-99862


Project Dates

  • Start Date
    5/26/2023


Notice of Intent Publication

  • NOI Publication Date
    5/26/2023


Record of Decision Publication

  • Initial Scheduled Date
    10/23/2026


Project Office Information

  • Lead Office
    State Office - NV
  • Offices
    Battle Mountain DO,   Bristlecone FO,   Carson City DO,   Ely DO,   Mount Lewis FO,   Sierra Front FO,   State Office - NV,   Stillwater FO


Contacts

  • Contact 1 Name
    Brian Buttazoni
  • Contact 1 Email
  • Contact 1 Phone
    (775) 861-6491