Late Mungers Integrated Vegetation Management Project
Project Type
DNA
NEPA Status
Completed - Completed
Lead Office
Grants Pass Field Office
Last Updated
What's New
The BLM conducted a 64-day public comment period on the draft Determination of NEPA Adequacy between April 28, 2022 and June 28, 2022.
On May 10, 2022 the BLM has posted an additional map book (Appendix 1) and Project map with labeled streams.
On May 10, 2022 the Grants Pass Field Office hosted a public webinar. There were approximately 12 speakers, and 34 members of the public in virtual attendance.
On May 14, 2022 the Grants Pass Field Office hosted a public field trip. There were approximately 24 members of the public in attendance.
On May 26, 2022 the BLM has posted Draft Resource Summaries referenced in the DNA.
On February 10, 2023 the BLM posted the final DNA and DR for the Late Mungers Integrated Vegetation Management Project. The appeal period will end on March 13, 2023.