NEPA Number: DOI-BLM-WO-2300-2022-0001-RMP-EIS
Project Name: 2021 Greater Sage-grouse Land Use Plan Amendments

Project Information 

  • NEPA Number
    DOI-BLM-WO-2300-2022-0001-RMP-EIS
  • Project Name
    2021 Greater Sage-grouse Land Use Plan Amendments
  • Project Type
    RMP Amendment - EIS
  • NEPA Status
    Completed - Completed
  • Lead Office
    WO-230
  • Last Updated


Project Description

What's New

Approved Resource Management Plans and Records of Decision have published!


The BLM has completed the Greater Sage-grouse Rangewide Planning effort and published Records of Decision for all remaining states on December 22, 2025. The approved Resource Management Plan (RMP) amendments and Records of Decision for all states are available in the Documents tab.


Additional information regarding this planning effort and more general greater sage-grouse information are available at https://www.blm.gov/sagegrouse. 





Draft EIS Publication

  • Initial Scheduled Date
    3/15/2024
  • Revised Target Date
  • Actual Date
    3/15/2024


Final EIS Publication

  • Initial Scheduled Date
    11/15/2024
  • Revised Target Date
  • Actual Date
    11/15/2024


Project Location

City State/Territory Zip Code County(ies)
Oakley Idaho 83346 Cassia County

Application Information

Project Dates

  • Start Date
    11/22/2021
  • End Date
  • FONSI Date


Notice of Intent Publication

  • Initial Scheduled Date
    11/22/2021
  • Revised Target Date
    11/22/2021
  • Actual Date
    11/22/2021


Record of Decision Publication

  • Initial Scheduled Date
    3/20/2025
  • Revised Target Date
  • Actual Date
    12/21/2025


Project Office Information

Contacts